Phew, it took several phone calls and a fax and finally Ashford sent the plumber to fix up his mistake.
Luckily the rain delayed the slab pour for a few days.
Now with the plumbing correct within the slab, we should be able to pour on Friday 15/5 , hey that's tomorrow !! so exciting. The house will have some real shape at last, even if it's only at ground level.
I ran into the owner of the concreting company who was looking at the final layout of the steelwork, he was waiting for the Building Inspector "D" to arrive. Hopefully to approve the steel.
Pic's of the completed Slab, boxed up and ready to go.
No comments:
Post a Comment