The Drama is that the Polystyrofoam blocks and steelwork has mostly been laid and the slab boxed up ready for a concrete pour on Tuesday ( last word I had from Ashford Homes ). They better not do that till the plumbing is fixed. Not sure what plans the plumber was working to. CR from Ashford homes told me the plumber was fixing this up on Friday - clearly not done.
During the week - slab area cleared- base material spread out - still have not fixed the plumbing Pwdr room
Some Photo's from Saturday - before the rain set in.
Pipe sticking up in the area where WIR for Bed 4 is to go. |