Wednesday, 5 October 2011

Power to the people......PV's installed

Day 200 - Week 32 - Our PV Panels and Inverter are now fully install and signed off just in time for the Vic Government PFit deadline of 30/9  It's up to SP Ausnet now to get the meter programmed for the feed in recording.


Growatt  3kW Inverter  combined with 16 x 190W MonoCrystalline PV Panels.  Facing 12deg East of north.....best day so far is 22kWhours.


The Shower screens are now installed, all the cupboard & WIR shelving fit out is now completed.

The painter has been back doing some trim up painting, the front door now with it's first coat of the final colour - Black.

The garage door now operational.

Good news on the Stone bench tops, they found another supplier and they have been made, fitting is due by this Friday 7th October.

Still no Dean the retaining wall guy - this weeks excuse  - the F7 rated timber had to be re sealed at the manufacturer's 'cause it did not come out right the first time....Hmmmm.... Yeah right.  He is running out of time - he could be organising the yet unfitted posts to be installed while he is waiting.

The ducted heating is booked for next week, so I'm told. See if this comes true.

Most items now ticked off the list - PCI  here we come, 2 weeks time  ?  See how they go.

More another Day :->>>>>>>>>>>>>>>>>>>

No comments:

Post a Comment