Wednesday, 23 March 2011

Pegging and Porta_Loo On site

Visited the site around 3pm today, the portable Loo and the site pegging are now on site.
After speaking with B the site supervisor on Monday 21/3, I thought they were going to do the retaining wall first. If they do the slab first , it will make it very hard to drill the post holes for the retaining wall given the house is only 1.0m from the retaining wall on this side.
The crossover protection has been installed now, a little late for the damage already done.
The site pegging looks secure, I did have to close the temp fencing up as they left it open in two spots.
Road Crossover protection installed
 Portable loo on site


North End pegging
 West Pegging