Day 174 -  The challenge is set, handover by 28/9 ? is this possible you say.  We have asked Ashford homes to get the house ready for handover by this date so we can install the PV panels to get in before the Vic government deadline of 30/9 for the premium feed-in tariff closure. Lets see if they rise to the challenge.

Painter has been and finished all of the internals, only the garage to go with the final coat.  Some patching to do here and there and some areas where some touch up is required. We are still to get to the bottom of the sealer issue - more on this in future blogs - I feel a paint inspection is due.



Several door not fully sealed as per BCV standards & tolerances one to chase up with SS

Electrical also stated in on Monday, looking good so far.

Still no retaining wall yet - there is a design for the rear section underway where the two walls join - hope to see this during this week.