Day 111, It's been a slow wet week, only a few minor items completed this last week. I now have a list of items to "get fixed" for SS at our meeting tomorrow. Let's see what the response is to the list. The build in 20 week's ideal timeframe is narrowing very fast and still lots to do. Where are we at ? Plaster cornice done, needs the final sanding. Trimming work materials delivered during the week, ready for eaves to be started, the raised floor area in the Theatre room to be constructed. The brickie is almost finished, he has been working on the Window Sills and the door step brickwork - still looking good.