The roof tilers were back and finished off the roof area. The plaster was due this week, but given the plumbers have not yet corrected the Hot Water system, the Plaster was delayed 1 week. We have a site meeting to discuss the HW issues this week coming - cannot wait to see what they say...!!! and explain why they have not yet fixed the Smart start system loop system. The ducted heating unit is now installed , not in the position marked on the drawings, but directly over the Theater room...hope this is not a noisy unit.
A few pic's to keep you up to speed.
Sound Batts Installed into the Theatre room walls |
heating ducts everywhere |
Hey Ernie, Looks like good progress, but a few off target shots in the finer details. Hope it all gets sorted out for you ok. Che
ReplyDeleteThanks Che, A lot happens in a short space of time - you need to keep an eye on what they are doing every few days.
ReplyDeleteYou mean the plumbers made some error in the plumbing installation? Well, I hope they will be able to fix all those errors. They must have a drawing or diagram of your home plumbing system so that you’ll know if things are in their proper places.
ReplyDelete>Elia Lester