Seems like the last week went so fast - we have more progress on the plumbing rough in - storm water and Agi drains behind the retaining wall are now setup. Mostly very good they way they are laid.....2 issues to resolve.
The final discharge point was not found by the plumber........they have just finished the pipes off at the property line, I can tell them the discharge point is about 5m to the west going off the old site photo's and the old bit of PVC out of the ground. Also one of storm water points is currently in the middle of the entrance to the garage, needs to be around 2.5m to the east to line up with the garage wall.........have to tell them about that one.
B from Ashford homes, mentioned last week the slab should get built this week coming...looking forward to this milestone.
Where they finished the SW incorrect....The real discharge point is under the cage somewhere.